FireBird Energy II Elizabeth Satellite: A High-Density Wolfcamp Development Signaling Early-Stage Cube Execution in the Midland Basin

FireBird Energy II LLC is a Midland Basin-focused operator executing a concentrated horizontal development program within Upton County. The Elizabeth Satellite project demonstrates how emerging Permian operators deploy multi-well pad drilling, structured execution sequencing, and centralized facility infrastructure to transition efficiently from drilling to production.


📍 Surface Persona – Sequenced Pad Development with Centralized Facility Buildout

Play: Permian Basin – Midland Sub-Basin
County: Upton County, Texas
Total Wells: 10

All wells are concentrated within a single lease footprint in the Midland Basin core:



Blocks / Sections

Development is clustered within a single survey area, with all wells falling inside a tight section/block footprint.

This confirms:

  • A contiguous leasehold position
  • No exploratory step-outs
  • A repeatable development zone

Lease Organization

LeaseWells
Elizabeth Satellite10

This single-lease structure indicates:

  • Centralized planning
  • Coordinated drilling and facility execution

Well Pad Configuration

Using the surface pad definition rule—wells within 50 meters of each other and sharing the same section/block—the wells group into 2 well pads:

Pad (Lease Based)Wells
Elizabeth Satellite Pad A (1201 A/B/C)5 wells
Elizabeth Satellite Pad B (1201 D/E/F)5 wells
  • Total Well Pads: 2
  • Average Wells per Pad: 5 wells

The pad design reflects a balanced dual-pad development strategy, enabling staged execution while maintaining operational efficiency.


🏭 Facility & Air Permit Integration

The development is anchored by a centralized production facility:

  • Facility Name: Elizabeth Satellite
  • Permit #: 183273
  • Permit Type: Standard Permit (STDPMT)
  • Action Type: New Registration (NOTIFYNEW)
  • Received Date: March 11, 2026
  • Status: Complete (same-day approval)
  • County: Upton County, Texas

Insight:

  • Confirms transition from drilling → production infrastructure
  • Same-day approval indicates standardized facility design
  • “Satellite” facility suggests:
    • Centralized handling of both pads
    • Likely tank battery / production hub configuration

Drilling Contractor Deployment by Pad

PadContractor / RigWells
Pad A (1201 A/B/C)Unit 4074
Pad A (1201 A/B/C)Cactus 4071
Pad B (1201 D/E/F)NorAm 265

Insight:

  • Pad A: Mixed rig deployment (Unit + Cactus)
  • Pad B: Single rig (NorAm 26) with full execution

👉 Indicates a transition from:

  • Multi-rig early phase → streamlined single-rig execution

Surface Persona (Summary)

The Elizabeth Satellite development represents a two-pad Midland Basin program executed on a single lease in Upton County, with pad classification based on wells sharing the same section/block and falling within 50 meters of each other. The surface design reflects a sequenced pad development model combining multi-rig execution on the first pad, single-rig efficiency on the second pad, and centralized facility infrastructure supporting both locations.


🔬 Sub-Surface Persona – Wolfcamp Horizontal Oil Development

Primary Field: Wolfcamp (Midland Basin)
Well Type: Horizontal oil wells
Total Wells: 10


Projected Depth Profile

  • Minimum Depth: ~10,200 ft
  • Maximum Depth: ~11,500 ft
  • Average Depth: ~10,900 ft
  • Total Feet Drilled (Planned): ~109,000 ft

The narrow projected depth range indicates consistent landing zones across the program.

Combined with pad density and section alignment, this strongly suggests:
👉 Co-development of stacked Wolfcamp benches


Sub-Surface Persona (Summary)

The Elizabeth Satellite project targets the Wolfcamp formation using standardized horizontal oil wells drilled to approximately 10,200–11,500 feet within a controlled depth window. The consistent depth profile and pad-based development indicate co-development of stacked benches designed to maximize reservoir recovery.


⏱ Project Cadence – Pad-Level Execution

📊 Activity Timeline

PhaseDate
First Activity DateAug 28, 2025
Last Activity DateSept 18, 2025
Total Activity Span21 days

Pad-Level Drilling Cadence

Pad A (1201 A/B/C)

  • Activity Window: Aug 28 → Aug 31
  • Span: 3 days
  • Avg Gap: ~0.75 days

👉 Fast batch drilling with overlapping operations


Pad B (1201 D/E/F)

  • Activity Window: Sept 14 → Sept 18
  • Span: 4 days
  • Avg Gap: 1.0 day

👉 Clean, sequential drilling (1 well per day cadence)


Drilling Sequence Insight

The development occurred in two distinct phases:

  1. Pad A (Late August):
    • Multi-rig deployment
    • Slightly irregular cadence
    • Likely initial execution phase
  2. Pad B (Mid-September):
    • Single rig (NorAm 26)
    • Highly consistent cadence
    • Optimized execution phase

Not Yet Drilled

  • 0 wells

👉 Fully drilled program (no backlog)


🏭 The Factory Workflow in Action

The Elizabeth Satellite program reflects a sequenced, pad-by-pad development model:

  • Permit Phase – Single-lease licensing
  • Pad A Execution – Multi-rig, early-stage development
  • Pad B Execution – Optimized single-rig drilling
  • Drilling Phase – High-speed cadence (~1 well/day on Pad B)
  • Facility Authorization – March 2026 air permit
  • Production Mode – Centralized facility supporting both pads

This progression shows a learning curve optimization, where execution improves between pads.


Strategic Takeaway

The Elizabeth Satellite development illustrates how FireBird Energy II is executing a concentrated Midland Basin program using a two-pad development strategy, stacked Wolfcamp targeting, and centralized facility infrastructure. The transition from mixed-rig drilling on the first pad to highly efficient single-rig execution on the second pad, combined with a centralized satellite facility, reflects a disciplined and evolving factory-style development model optimized for repeatability and speed.