Continental Resources Project Overview – UTL 4139 Development (Winkler County, TX)

This project highlights a phased Permian development model where licensing, pad construction, and facility deployment are aligned ahead of drilling. The result is a structured multi-pad program transitioning from pilot to full-scale development.

Continental Resources is transitioning from a completed pilot pad to a fully permitted, multi-pad Wolfcamp development in Winkler County, with infrastructure already approved ahead of drilling. With 10 wells not yet drilled and facilities in place, the project is entering a near-term execution phase, signaling an active window for development and vendor engagement.


Pad-Level Development Structure

PadWellsStatusContractorPhase
Pad 03Drilled (Jan 2024)Scan VisionPilot Development
Pad 15Not DrilledExpansion Phase
Pad 25Not DrilledFull Development

Drilling Cadence by Pad

PadFirst ActivityLast ActivitySpan (Days)Avg Days Between WellsNot Drilled
Pad 0Jan 18, 2024Jan 19, 202410.50
Pad 15
Pad 25

Overall Project Cadence

MetricValue
Total Wells13
First ActivityJan 18, 2024
Last ActivityJan 19, 2024
Total Duration1 day
Not Yet Drilled10

Full Development Cadence (License → Activity → Facility)

MetricValue
First License DateDec 11, 2023
Latest License DateApr 14, 2026
Air Permit DateApr 21, 2026
License → Facility Lag~7 days
Activity → FacilityPre-drill alignment

Key Cadence Insight

  • Pad 0 → completed in a tight 1-day drilling window
  • Pads 1 & 2 → fully permitted but not yet drilled
  • Facility permit → approved same day (0-day cycle)

👉 Interpretation:

  • No delay between regulatory steps
  • Infrastructure is staged before drilling begins
  • Operator is preparing for next drilling phase

Surface Persona: What the Location Tells Us

Geography

  • County: Winkler County, TX
  • Play: Permian Basin – Delaware (Wolfcamp / Phantom Field)

Land Pattern

  • Single-section development
  • Block: 21
  • Abstract: U81
  • Section: 41

Surface Strategy

  • Multi-pad development within same section
  • Sequential lease progression (A–M)
  • Centralized facility (CTB)

Surface Persona

A single-section, high-density Permian development where Continental is executing a phased multi-pad drilling strategy supported by centralized infrastructure and sequential lease development.


Sub-Surface Persona: What the Reservoir Tells Us

Formation

  • Phantom Field (Wolfcamp)

Well Design

  • 100% horizontal wells
  • Oil & gas production focus

Depth Profile

PadMinMaxAvgRange
Pad 011,50012,20011,833700 ft
Pad 111,55012,15411,798604 ft
Pad 211,55012,15411,855604 ft

Sub-Surface Insight

  • Tight depth ranges across all pads
  • Identical well design and landing zone
  • No variation between pads

Sub-Surface Persona

A standardized horizontal Wolfcamp drilling program targeting a consistent landing zone with repeatable well design and minimal geological variability.


Are They Using Co-Development?

From the Data:

  • Same section
  • Same formation (Wolfcamp)
  • Tight depth range
  • Identical well profiles

👉 Conclusion: NO co-development

This is:

  • Single-zone targeting
  • Maximum repeatability
  • Efficiency-driven development

Facility Signal: Transition to Next Phase

EventDateDays
Latest LicenseApr 14, 2026
Air Permit ApprovedApr 21, 2026~7 days

Facility Insight

  • Facility Type: Central Tank Battery (CTB)
  • Permit Type: Notification (instant approval)
  • Timing: Before drilling starts

Interpretation

  • Facilities are pre-engineered and standardized
  • Infrastructure is staged ahead of drilling
  • No regulatory delays

End-to-End Development Model

Phase 1: Pilot Development

  • Small pad (3 wells)
  • Tight execution window (1 day)
  • Contractor established

Phase 2: Permit Buildout

  • 10 additional wells permitted
  • Sequential lease expansion
  • Multi-pad planning completed

Phase 3: Facility Alignment

  • Air permit approved instantly
  • Infrastructure ready before drilling

Phase 4 (Next Expected Step)

  • Drilling mobilization on Pads 1 & 2

What This Project Shows

What the Data Signals

  • Phased development (pilot → scale)
  • Multi-pad, single-section strategy
  • Standardized well design
  • Pre-aligned infrastructure

Key Insight

Continental is operating a pre-staged development model:

  • Pilot executed → validated design
  • Inventory built → permits secured
  • Facilities approved → ready for deployment
  • Drilling → imminent

Final Takeaway

This project reflects a modern Permian development approach, but with a key distinction from fully synchronized models:

  • NOT continuous drilling yet
  • Instead → staged execution with pre-built inventory

Development Profile

  • Pilot-first strategy
  • High-density single-section development
  • Standardized Wolfcamp drilling
  • Infrastructure aligned ahead of execution
  • 10 wells in near-term drilling queue

Commercial Insight (Most Important)

👉 This project is currently in:

“Pre-Drill Execution Window”

  • Permits → COMPLETE
  • Facilities → READY
  • Drilling → NOT STARTED

What This Means

This is the highest-value sales timing window:

  • Vendors being selected
  • Budgets already allocated
  • Execution about to begin

Bottom Line

Continental is preparing to transition from pilot validation to full-scale pad development in Winkler County.

👉 The next phase is not speculative — it is imminent execution.