Operational Results
Chesapeake second quarter net production was approximately 3,653 mmcfe per day (96% natural gas and 4% total liquids), utilizing an average of 12 rigs to drill 53 wells and place 27 wells on production.
Oil & Gas Data Download
Chesapeake Wells Drilled 2023
Chesapeake Rig Count July 2023
Haynesville Account List
Detailed list of accounts that drilled wells in the Haynesville
Marcellus Account List
Detailed list of accounts that drilled wells in the Marcellus
Chesapeake is currently operating nine rigs including four in the Marcellus and five in the Haynesville. As previously announced, the company released a rig from the Marcellus at the beginning of the third quarter and another from the Haynesville this week. Drilling operations in the Eagle Ford asset have concluded for the year.
The company is currently operating one frac crew in the Marcellus and one in the Haynesville having released one crew each from the Marcellus, Haynesville, and Eagle Ford in the second or beginning of the third quarter.
Chesapeake continued to build upon its peer leading operational performance, recognizing additional efficiency improvements during the second quarter. In the Marcellus, the company drilled three of the five fastest wells in its history, including the fastest well, a 10,383-foot lateral to a total depth of 17,083 feet in less than eight days. In the Haynesville, continuous pumping technology employed in 2023 has led to a greater than 20% increase in efficiencies relative to previous zipper operations. In addition to the multiple D&C performance records, the combined employee and contractor Total Recordable Incident Rate for the first half of 2023, was more than 50% improved from the same time period last year.
The company expects to drill 30 to 40 wells and place 40 to 50 wells on production in the third quarter of 2023. The company’s operating plan remains flexible and is prepared for further adjustments based on market conditions.
Year-to-date, the company has acquired 10,000 net acres through its ongoing leasing program in the Marcellus and Haynesville at an average cost of $2,400 per acre.
On its continued path to Be LNG Ready, the company entered into a Heads of Agreement (HOA) with Energy Transfer LP’s Lake Charles LNG project. Under the agreement, Chesapeake will supply to Lake Charles LNG volumes of natural gas sufficient to produce up to 1.0 mtpa of LNG which, post liquefaction, would be purchased by Gunvor at a price indexed to JKM for a period of 15 years.