A One-Year Journey from Licensing to Production Infrastructure
Modern shale development is increasingly defined by manufacturing-style execution, where operators develop multiple pads, drill wells in sequence, and centralize production infrastructure to improve efficiency and reduce costs.
A recent project by Greenlake Energy Operating, LLC in Reeves County, Texas provides an excellent example of this approach. Over roughly twelve months, the company progressed from well permitting to drilling operations and ultimately to construction of a centralized production facility supporting multiple pads.
Located in the heart of the Delaware Basin, the western sub-basin of the Permian Basin, the project targeted Wolfcamp and Wolfbone reservoirs through a coordinated multi-pad co-development strategy.

The Surface Development Plan
The project consisted of two multi-well pads located within Block 51 T8S in Reeves County.
Mike Jones Pad
- Section 40
- 3 horizontal wells
- Leases: Mike Jones and Mike Jones A
Paul Wall Pad
- Section 26
- 3 horizontal wells
- Lease: Paul Wall
Using a 50-meter surface location rule, the six wells grouped into two distinct surface pads. Both pads were located within the same block and acreage position, indicating a coordinated development plan rather than isolated drilling activities.
This type of development has become common throughout the Delaware Basin, where operators seek to maximize capital efficiency by drilling multiple wells from centralized locations while minimizing environmental footprint and infrastructure duplication.
Delaware Basin Target Zones
The wells targeted two of the basin’s most productive unconventional reservoirs:
Wolfcamp Development
The Mike Jones pad was developed within the HOEFS T-K (Wolfcamp) field.
Wolfbone Trend Development
The Paul Wall pad targeted the Wolfbone Trend Area.
All six wells were planned as horizontal wells and exhibited remarkably consistent projected depths.
Pad Wells Average Projected Depth Mike Jones 3 10,700 ft Paul Wall 3 10,800 ft
Total planned footage across the project exceeded 64,500 feet.
The similarity in depth, geology, and development timing strongly suggests a co-development strategy focused on maximizing resource recovery from stacked Wolfcamp and Wolfbone intervals.
From Permit to Rig Mobilization
The first well license was issued on July 14, 2025.
Drilling activity began shortly thereafter.
Drilling Contractor
- Helmerich & Payne (H&P)
Rig
- H&P Rig 261
The same drilling rig was utilized across both pads, further supporting the conclusion that Greenlake executed the project as a single coordinated drilling campaign.
Development Cadence
| Milestone | Timing |
|---|---|
| First License | July 14, 2025 |
| First Spud | August 28, 2025 |
| Last Spud | October 12, 2025 |
| Average License to First Spud | 49.5 Days |
The Mike Jones pad moved from licensing to spud in approximately 45 days, while the Paul Wall pad followed roughly 54 days after licensing.
This cadence is typical of Delaware Basin operators working to optimize rig utilization and maintain continuous development schedules across adjacent acreage positions.
Evidence of a Multi-Pad Co-Development Strategy
Several indicators point to a deliberate co-development program:
- Common acreage position within Block 51 T8S
- Adjacent sections
- Identical drilling contractor
- Same drilling rig
- Similar projected depths
- Horizontal well designs
- Sequential drilling schedule
- Shared production facility
Rather than treating each pad as an independent project, Greenlake appears to have developed the acreage as a unified manufacturing operation.
This approach reduces rig mobilization costs, streamlines completion activities, and supports centralized production infrastructure.
Transitioning from Drilling to Production
The next major milestone occurred nearly a year after the first permits were issued.
On June 19, 2026, Greenlake received and completed Air Permit Project #411196 for the:
MIKE JONES PAUL WALL FACILITY
The permit was issued under a Non-Rule Standard Permit registration and supports long-term production operations in Reeves County.
Air Permit Highlights
- Project Number: 411196
- Permit Number: 184429
- Status: Issued and Complete
- Received Date: June 19, 2026
- Operator: Greenlake Energy Operating, LLC
- County: Reeves County, Texas
- Permit Term: 10 Years
The timing of the permit is noteworthy.
Approximately:
- 340 days after the first well license
- 295 days after the first spud
- 250 days after the final spud
The permit marks the project’s transition from drilling and completion into sustained production operations.
What the Facility Reveals
Recent aerial imagery of the site provides insight into the project’s current stage of development.
The facility appears substantially built and includes:
Production Equipment
- Multiple horizontal separator vessels
- Process piping and manifold systems
- Production headers
- Instrumentation infrastructure
Storage Infrastructure
- Four large vertical storage tanks
- Containment systems
- Associated production piping
Construction Activity
The image also shows:
- Numerous pickup trucks
- Crane and lifting equipment
- Material staging areas
- Active workforce presence
The site appears to be in the late construction or commissioning phase.
The scale of the facility suggests it was designed to receive production from both the Mike Jones and Paul Wall pads through a centralized gathering and processing configuration.
This hub-and-spoke model has become increasingly common throughout the Delaware Basin as operators seek to reduce operating costs while improving production efficiency.
Final Takeaway
The Greenlake Energy Mike Jones and Paul Wall development demonstrates how modern Delaware Basin operators execute shale projects through disciplined, repeatable development programs.
Beginning with two three-well pads targeting Wolfcamp and Wolfbone intervals, the company utilized H&P Rig 261 to drill six horizontal wells across adjacent acreage positions. Roughly a year later, the project advanced into the production infrastructure phase with the permitting and construction of a centralized production facility.
From licensing to drilling and ultimately to facility construction, the project reflects the evolution of shale development into a manufacturing-style process—one built on pad drilling, co-development, centralized infrastructure, and efficient capital deployment.
For service companies, midstream providers, equipment suppliers, and investors, projects like this provide a clear roadmap of how today’s Delaware Basin developments progress from permit to production.



