Overview
We collect Texas pipeline permits and air permits related to facilities, we post the data weekly.
Project Summary
Texas oil & gas pipeline and facility project permits last 7 days report dated June 1 2021 is tracking 32 Oil & Gas and Mid Stream Operators that had 62 pipeline and facilities approved permits.
- Top Oil & Gas Operators approved for a facility permits include; Diamondback Energy (17), Hibernia Resources, LLC (6), Crownquest Operating, LLC (4), FOURPOINT ENERGY LLC (3)
- Top Counties approved for a facility permits include; Martin (18), Reagan (6), Loving (3), Dewitt (2)
- Top Oil & Gas Operators approved for a pipeline permits include; ENTERPRISE Products (2), HUGOTON OPERATING COMPANY, INC. (2), Matador Resources Company (1)
Texas pipeline and facility project Download
Permit Details
Texas Pipeline Projects
Pipeline permits include gathering or transport pipelines of a liquid, gas or oil through a system of pipes. In addition to these main types of pipelines, there are also four other sub-categories of pipelines: Gathering Lines, Feeder Lines, Transmission Pipelines and Distribution Pipelines. The permits represent all types of pipelines. Source Texas pipeline and facility project permits June 1 2021
Texas T4 Pipeline Permits
Texas Pipeline Construction
Texas Oil & Gas Facility Permits
Facilities are a system of vessels, piping, valves, tanks and other equipment that are used to gather, process, measure, store or dispose of petroleum, natural gas or water. … The upstream facility network includes equipment for the handling of oil, natural gas, natural gas liquids, and water. Source Texas pipeline and facility project permits May 25 2021
We have 3 types of permits related to construction of new facilities the Permit Type is related to the stage of the project.
- Notify New – Prior to construction, a notification with basic information must be submitted.
- Initial -Ninety days after submitting the Initial Project Notification, a more detailed registration for the standard permit is required. This could be related to existing plant maintenance
- Revision – Permit approved with a revision to the permit. This could be related to existing plant maintenance
Texas Facility Transfers
Free Weekly Pipeline & Facility Reports
* These fields are required.
Facility and Pipeline Project Details
Texas Facilities Interesting Projects
Apache has a new battery permit close to Rankin permit #RN111266300.
They recently drilled 2 wells in the region. In 2010 Apache, acquired Mariner Energy giving them a position in the Spraberry.
Source Texas pipeline and facility project permits June 1 2021
Devon has two new permits north of Orla Texas. Permit #RN111266474 & #RN111266482
They are very active drilling wells in the area.
Source Texas pipeline and facility project permits June 1 2021
Enterprise Products has two permits related to existing compressor stations YEARY COMPRESSOR STATION & RACHAL COMPRESSOR STATION Permit #RN102302718 & #RN102523537
Texas Pipeline Projects
Nuevo pipeline permit #9244 renewal of a 96 mile pipeline
Nuevo Midstream’s operations in the Delaware Basin began in April 2011, when the company acquired a 130-mile gas gathering system and, later that year, reactivated a small J-T processing plant.
At the time of its sale to Western Gas in October 2014, Nuevo’s assets included 300 million cubic feet per day (MMcf/d) of operational cryogenic processing capacity at its Ramsey processing complex in Reeves County, Texas; 1,800 gallons per minute (gpm) of treating capacity; four field compressor stations; and a 275-mile gas gathering system that spanned a five-county area. An additional 30 miles of gathering pipeline was under construction with an additional 400 MMcf/d of processing capacity purchased and scheduled to come into service in 2015.
Nuevo’s gathering and processing system was supported by long-term acreage dedications of approximately 150,000 acres and volume commitments from 47 producers operating in an area with multiple, stacked pay zones. Nuevo’s producer customers included numerous blue-chip shale developers operating substantial drilling and development programs.
Penn Virginia pipeline permit renewal #8501 total distance 121 miles.
Penn Virginia Corporation is an independent oil and gas company engaged in the exploration, development and production of oil, NGLs and natural gas in various domestic onshore regions of the United States, with a primary focus in the Eagle Ford Shale in South Texas. Penn Virginia recently relocated its corporate headquarters from Radnor, Pennsylvania to Houston, Texas.
Merit Energy renewal pipeline permit 5687 distance #1448 miles
Merit Energy’s merit pay is dependent on its success in developing oil and gas projects. The company acquires, develops, and operates mature producing oil and gas properties on behalf of equity-based limited partnerships. Merit Energy has eight core operating areas in North America. It manages assets in a dozen US states (primarily in the Rockies, Mid-Continent, and the South and Southwest). The company has estimated proved reserves of 419 million barrels of oil equivalent and production of 65,000 barrels of oil equivalent per day. It has interests in more than 11,000 wells.
Enterprise Products Partners L.P. is one of the largest publicly traded partnerships and a leading North American provider of midstream energy services to producers and consumers of natural gas, natural gas liquids (“NGLs”), crude oil, refined products and petrochemicals. Our services include: natural gas gathering, treating, processing, transportation and storage; NGL transportation, fractionation, storage and import and export terminals; crude oil gathering, transportation, storage and terminals; petrochemical and refined products transportation, storage and terminals; and a marine transportation business that operates primarily on the United States inland and Intracoastal Waterway systems.
Enterprise Products Partners permit #7403 renewal pipeline distance 473 miles
ENTERPRISE PRODUCTS pipeline permit #3883 renewal 2800 miles
Sign-up for weekly project updates
* These fields are required.